Information reviewed: 16 November 2026

An instruction to “produce an LOD 300 Revit model” leaves several important questions unanswered. Which elements are included? How closely must they represent the observed building? Which information is needed for the next decision? Our Scan to BIM service should be commissioned with an element-based brief rather than a single label applied to the whole building.

Existing building bim — illustration
Illustrative view: existing building bim.

What the LOD labels describe

BIMForum uses LOD to mean Level of Development. In broad terms, 200 concerns approximate representation, 300 specific geometry, 350 relevant interfaces and 400 fabrication or assembly detail. These descriptions do not independently establish survey accuracy, concealed construction or the completeness of a model.

Level Practical commissioning question
LOD 200 Is approximate representation enough for the intended decision?
LOD 300 Which elements require specific size, shape, location and orientation?
LOD 350 Which connections or interfaces need explicit coordination information?
LOD 400 Is fabrication or assembly information actually available and required?

The table is an interpretation for briefing, not a replacement for the relevant BIMForum definitions. A scan of finished surfaces does not provide all the information needed to author fabrication-ready components.

Accuracy is a separate requirement

An element can be richly modelled yet positioned incorrectly. Another can be deliberately simple but accurately located. Specify the required relationship between model geometry and surveyed evidence separately from the development level.

If a project uses “LOA”, identify the exact framework, edition and measurement criteria. Do not assume that every supplier uses the same meaning or that an LOD number implies an LOA. A model brief should also explain how deviations are tested and how inaccessible or assumed elements are identified.

Use an element matrix

Element Intended use Information to agree
External walls Layout and façade coordination Observed faces, irregularity, openings and simplification rules
Floors Vertical coordination Reference surfaces, level changes and treatment of unknown build-up
Roof Loft feasibility Visible slopes, accessible structure and hidden-area limitations
Stairs Circulation coordination Flights, landings, headroom and critical dimensions
Services Space coordination Named visible systems, access and whether sizes are observed or assumed

This matrix is often more useful than requesting the highest available LOD everywhere. Model the information that will be used, and record the information that is not known. An attractive family should not make an unverified component look certain.

Structural junction model — illustration
Illustrative view: structural junction model.

Level of information need

ISO 7817-1:2024 provides a framework for defining level of information need, covering more than geometry alone. It does not impose a universal LOD on every UK refurbishment. In practical terms, explain who needs the information, when they need it and which decision it supports.

For example, a feasibility study might need the roof envelope and main level relationships. A later coordination task may need specific roof-to-wall interfaces. The second task should be briefed as additional information, not assumed to exist because the initial file was called a BIM model.

Existing buildings need explicit unknowns

Scanning usually observes finished surfaces. It does not automatically reveal wall layers, reinforcement, concealed connections or equipment behind enclosures. Agree how unknown thicknesses and materials are represented. Use clearly identified placeholders where appropriate rather than silently inventing construction.

Before modelling, agree Revit version, coordinates, levels, naming, model splitting, linked files and required exports. Then review a representative area early. A sample containing a typical wall, stair and awkward junction can reveal interpretation differences before the entire model is produced.

Acceptance and cost control

Check representative elements against the survey evidence, inspect critical interfaces and test the files in the receiving environment. Review the limitations register alongside the model. Our QA guide explains why a low registration residual does not, by itself, validate every modelled element.

More elements, greater complexity and tighter verification requirements can increase effort, but there is no universal “LOD 400 costs three times more” rule. Reduce unnecessary work by prioritising project decisions. Compare CAD and BIM workflows, and use our survey samples to discuss the expected result.

Model development comparison — illustration
Illustrative view: model development comparison.

Frequently asked questions

Does LOD 350 mean more accurate than LOD 300?

Not automatically. The development description and positional accuracy requirement address different questions. Specify both.

Can downloaded Revit families improve an existing-condition model?

Our Revit family downloads can help authoring, but a convenient family is not evidence of the surveyed object’s exact geometry or properties. Validate its suitability and keep unverified information explicit.

What should I send for a BIM quotation?

Send an element list, intended uses and sample requirements, together with available survey data, required version, accuracy expectations and deadline. Include the receiving team’s model standard if one exists.

References and review date

References checked on 16 November 2026. Requirements can change; confirm the applicable edition and project-specific requirements when appointing the team.